Establish the geographical extent of the LCWIP, and arrangements for governing and preparing the plan.
Gathering information
January 2021
-
June 2021
Identify existing patterns of walking and cycling and potential new journeys. Review existing conditions and identify barriers to cycling and walking. Review related transport and land use policies and programmes.
Network planning for cycling
July 2021
-
November 2021
Identify origin and destination points and cycle flows. Convert flows into a network of routes and determine the type of improvements required.
Network planning for walking
July 2021
-
November 2021
Identify key trip generators, core walking zones and routes, audit existing provision and determine the type of improvements required.
Prioritisation of improvements
June 2022
-
October 2022
Prioritise improvements to develop a phased programme for future investment. The current engagement forms part of this stage, and will be used to review the work conducted to date.
Integration and Application
November 2022
-
June 2023
Integrate outputs into local planning and transport policies, strategies, and delivery plans.